2025年,丹麦获得欧盟批准的一项价值 38 亿欧元的 CCS 补贴计划,以支持大规模的捕集与封存。该框架侧重于生物源二氧化碳 (NECCS) 和大规模化石捕集,使丹麦通过 Greensand 等项目成为中欧封存枢纽。
National Governance Context
丹麦 Overview
Aggregate National Maturity Index (Peak Strength)
Governed Policies
2
Identified Projects
37
Operational Cap 0.0 Mtpa
Under Construction Cap 16.0 Mtpa
Planned Cap 86.8 Mtpa
Related Policy Network
Peer Frameworks
Directly Linked Assets
Thorning storage
碳封存 — 0 Mtpa
Kredsløb Energipark Lisbjerg
碳捕集 — 0.36 Mtpa
HOFOR Amagerværket
碳捕集 — 0.9 Mtpa
BioCirc biogas plant
碳捕集 — 0.131 Mtpa
Sindal Biogas Hjørring Municipality
碳捕集 — 0 Mtpa
Fjernvarme Fyn
碳捕集 — 0.28 Mtpa
Fjord-Projekt CIP (Carbon Captured from Nordværk Incineration Plant)
碳利用 — 0.33 Mtpa
A2X's CCS Esbjerg (Carbon captured from Energnist Incineration Plant in Esbjerg)
全流程项目 — 0.23 Mtpa
European Energy/Brønderslev PtX (Biogas or waste incineration plants in Northern Jutland)
碳利用 — 0.15 Mtpa
CopenCapture (CopenHill Wate to Energy Plant)
全流程项目 — 0.4 Mtpa
Grenaa Port phase 2
碳运输 — 10 Mtpa
Grenaa Port phase 1
碳运输 — 0 Mtpa
CO2 Storage Kalundborg
运输与封存 — 12 Mtpa
Projekt Greenstore
运输与封存 — 0 Mtpa
AffaldPlus Affaldsenergi
碳捕集 — 0.15 Mtpa
Project Bifrost Phase 1
运输与封存 — 3 Mtpa
Greensand Future phase 1
运输与封存 — 0.4 Mtpa
Project Greensand phase 2
运输与封存 — 7.6 Mtpa
Vestforbrænding's Ejby Glostrup incineration plant
碳捕集 — 0.5 Mtpa
Avedøre Power Station CCS
碳捕集 — 0.15 Mtpa
Gassum storage/Fyrkat network (Norne carbon storage hub)
碳封存 — 2.6 Mtpa
Havnso storage/Trelleborg network (Norne carbon storage hub)
碳封存 — 16.4 Mtpa
Port of Aalborg terminal and pipeline to Fyrkat (Norne carbon storage hub)
碳运输 — 15 Mtpa
Port of Kalundborg terminal and pipeline to Trelleborg phase 1 (Norne carbon storage hub)
碳运输 — 4 Mtpa
Port of Kalundborg terminal and pipeline to Trelleborg phase 2 (Norne carbon storage hub)
碳运输 — 8 Mtpa
Project Bifrost Phase 2
运输与封存 — 10 Mtpa
Kalundborg refinery project
碳捕集 — 0 Mtpa
ACCSION Aalborg Portland
碳捕集 — 1.4 Mtpa
ARGO waste-to-energy plant
碳捕集 — 0.35 Mtpa
BIOFOS Carbon Capture Project
碳捕集 — 0 Mtpa
Asnæs Power Station
碳捕集 — 0.28 Mtpa
Avedøre Power Station CCU (Green Fuels for Denmark)
碳利用 — 0 Mtpa
Fortum waste solutions Nyborg
碳捕集 — 0.17 Mtpa
Project Ruby (Rodby) phase 1
碳封存 — 1 Mtpa
Project Ruby (Rodby) phase 2
碳封存 — 6.5 Mtpa
Stenlille project (CO2RYLUS)
碳封存 — 0.5 Mtpa
Amager Bakke/Amager Resource Centre (ARC)
碳捕集 — 0.5 Mtpa