Facilities / Denmark / T&S

Greensand Future phase 1

Under construction Phase: 1 Hub: Greensand
Consortium Partners: INEOS E&P (40%)Nordsøfonden (20%)Royal Wagenborg (ship)Welltec (storage)Wintershell Dea (Harbour Energy) (40%)

Asset Description

Project Overview

This t&s project is located in Denmark (Europe) and is currently Under construction. The primary sector classification is T&S. The reported fate of captured carbon is Dedicated storage. The project is associated with the Greensand hub. Announcement year: 2020. Final investment decision year: 2024. Planned or actual operation year: 2026. Reported partners: INEOS E&P (40%), Wintershell Dea (Harbour Energy) (40%), Welltec (storage), Royal Wagenborg (ship), Nordsøfonden (20%).

Governing Policy Ecosystem