Database / Denmark / 2025

Danish CCS Subsidy Scheme 2025

Incentive Active Verified

In 2025, Denmark secured EU approval for a €3.8 billion CCS subsidy scheme to support massive capture and storage. The framework focuses on biogenic CO2 (NECCS) and large-scale fossil capture, positioning Denmark as a central European storage hub with projects like Greensand.

National Governance Context

Denmark Overview

Aggregate National Maturity Index (Peak Strength)

Governed Policies

2

Identified Projects

37

Operational Cap 0.0 Mtpa
Under Construction Cap 16.0 Mtpa
Planned Cap 86.8 Mtpa

Related Policy Network

Directly Linked Assets

Thorning storage

Storage — 0 Mtpa

Kredsløb Energipark Lisbjerg

Capture — 0.36 Mtpa

HOFOR Amagerværket

Capture — 0.9 Mtpa

BioCirc biogas plant

Capture — 0.131 Mtpa

Sindal Biogas Hjørring Municipality

Capture — 0 Mtpa

Fjernvarme Fyn

Capture — 0.28 Mtpa

Fjord-Projekt CIP (Carbon Captured from Nordværk Incineration Plant)

CCU — 0.33 Mtpa

A2X's CCS Esbjerg (Carbon captured from Energnist Incineration Plant in Esbjerg)

Full chain — 0.23 Mtpa

European Energy/Brønderslev PtX (Biogas or waste incineration plants in Northern Jutland)

CCU — 0.15 Mtpa

CopenCapture (CopenHill Wate to Energy Plant)

Full chain — 0.4 Mtpa

Grenaa Port phase 1

Transport — 0 Mtpa

Grenaa Port phase 2

Transport — 10 Mtpa

CO2 Storage Kalundborg

T&S — 12 Mtpa

Projekt Greenstore

T&S — 0 Mtpa

AffaldPlus Affaldsenergi

Capture — 0.15 Mtpa

Project Bifrost Phase 1

T&S — 3 Mtpa

Greensand Future phase 1

T&S — 0.4 Mtpa

Project Greensand phase 2

T&S — 7.6 Mtpa

Vestforbrænding's Ejby Glostrup incineration plant

Capture — 0.5 Mtpa

Avedøre Power Station CCS

Capture — 0.15 Mtpa

Gassum storage/Fyrkat network (Norne carbon storage hub)

Storage — 2.6 Mtpa

Havnso storage/Trelleborg network (Norne carbon storage hub)

Storage — 16.4 Mtpa

Port of Aalborg terminal and pipeline to Fyrkat (Norne carbon storage hub)

Transport — 15 Mtpa

Port of Kalundborg terminal and pipeline to Trelleborg phase 1 (Norne carbon storage hub)

Transport — 4 Mtpa

Port of Kalundborg terminal and pipeline to Trelleborg phase 2 (Norne carbon storage hub)

Transport — 8 Mtpa

Project Bifrost Phase 2

T&S — 10 Mtpa

Kalundborg refinery project

Capture — 0 Mtpa

ACCSION Aalborg Portland

Capture — 1.4 Mtpa

ARGO waste-to-energy plant

Capture — 0.35 Mtpa

BIOFOS Carbon Capture Project

Capture — 0 Mtpa

Asnæs Power Station

Capture — 0.28 Mtpa

Avedøre Power Station CCU (Green Fuels for Denmark)

CCU — 0 Mtpa

Fortum waste solutions Nyborg

Capture — 0.17 Mtpa

Project Ruby (Rodby) phase 1

Storage — 1 Mtpa

Project Ruby (Rodby) phase 2

Storage — 6.5 Mtpa

Stenlille project (CO2RYLUS)

Storage — 0.5 Mtpa

Amager Bakke/Amager Resource Centre (ARC)

Capture — 0.5 Mtpa