Targeting 4-8 Mtpa by 2030 through Carbon Contracts for Difference (CCfDs) and strategic North Sea storage agreements.
National Governance Context
France Overview
Aggregate National Maturity Index (Peak Strength)
Governed Policies
2
Identified Projects
30
Operational Cap 0.0 Mtpa
Under Construction Cap 0.1 Mtpa
Planned Cap 30.7 Mtpa
Related Policy Network
Directly Linked Assets
3D DMX ArcelorMittal and IFPEN Dunkirk (full-scale)
Capture — 0.7 Mtpa
Hynovera
CCU — 0.123 Mtpa
eCapt-Rhone LeTeil
CCU — 0.2 Mtpa
Grand Ouest CO2 (GOCO₂) transport
Transport — 2.6 Mtpa
Neau Lime plant
Capture — 1.6 Mtpa
Saint-Pierre-la-Cour cement plant
Capture — 1 Mtpa
Natran Group CO2 backbone
Transport — 5 Mtpa
Grandpuits DAC hub
Full chain — 0.1 Mtpa
CarboClearTech (Martres-Tolosane cement plant)
Capture — 0.7 Mtpa
D'Artagnan Dunkirk CO2 Hub Phase 1
Transport — 1.5 Mtpa
D'Artagnan Dunkirk CO2 Hub Phase 2
Transport — 1.4 Mtpa
D'Artagnan Dunkirk CO2 Hub Phase 3
Transport — 5.6 Mtpa
BEA Alizay
CCU — 0.35 Mtpa
Papetier Sylvamo Saillat sur Vienne
CCU — 0.6 Mtpa
ReSTart Usine RYAM Tartas
CCU — 0.33 Mtpa
AirvaultGoCO2 cement plant
Capture — 1 Mtpa
Oak CCS (RepAir Carbon- C-Questra) Phase 1
Capture — 0.03 Mtpa
Oak CCS (RepAir Carbon- C-Questra) Phase 2
Capture — 0.07 Mtpa
VAIA project Montalieu-Vercieu site
Full chain — 1.2 Mtpa
K6 Program- Lumbres cement plant
Capture — 0.81 Mtpa
CalCC Lhoist Air Liquide Lime plant Réty
Capture — 0.7 Mtpa
PYCASSO hub phase 1 - eastern and western pipeline
T&S — 1 Mtpa
Gonfreville Raffinerie
Capture — 0.5 Mtpa
VAIA HyNoVi project (Vicat Montalieu plant)
CCU — 0.5 Mtpa
Grandpuits biorefinery
CCU — 0.11 Mtpa
Arcelor Mittal Air Liquide Low-carbon steel
Capture — 1 Mtpa
ECO2Normandy phase 1
Transport — 3 Mtpa
3D DMX ArcelorMittal and IFPEN Dunkirk 'REUZE'
CCU — 0.3 Mtpa
Aluminium Dunkerque feasibility study
Capture — 0.24 Mtpa
Waste-to-energy Aker Carbon Capture (unknown facility)
Capture — 0.2 Mtpa