Database / Norway / 2020

Norway Longship Full-Scale CCS Project

法律监管 现行 Verified

Norway launched Longship on 21 September 2020 as a state-supported full-scale CCS demonstration covering industrial capture, ship transport, intermediate storage and permanent offshore geological storage through Northern Lights. Government project information was updated in 2024, but the underlying policy decision and launch date are from 2020.

National Governance Context

Norway Overview

Aggregate National Maturity Index (Peak Strength)

Governed Policies

5

Identified Projects

54

Operational Cap 3.6 Mtpa
Under Construction Cap 4.0 Mtpa
Planned Cap 90.9 Mtpa

Related Policy Network

Directly Linked Assets

CO2 TO METHANOL Finnfjord Ferrosilicon

CCU — 0.3 Mtpa

Equinor Mongstad refinery

Capture — 0 Mtpa

Celsio CCS project terminal

Transport — 0.4 Mtpa

Eramet Sauda

Capture — 0.26 Mtpa

Stakraft Varme Heimdal (Trondheim)

Capture — 0.22 Mtpa

Returkraft Kristiansand

Capture — 0.13 Mtpa

Climeworks Enova DAC+S plant

Capture — 0 Mtpa

Rana ferrosilicon smelter capture

Capture — 1.5 Mtpa

Rana ferroglobe

Capture — 3.7 Mtpa

Eramet Manganese Porsgrunn phase 2

Full chain — 0 Mtpa

Iroko carbon storage

Storage — 7.5 Mtpa

Kinno carbon storage (EXL010)

Storage — 5 Mtpa

Albondigas carbon storage (EXL008)

Storage — 5 Mtpa

Atlas carbon storage

Storage — 0 Mtpa

Kaupang carbon storage (EXL012)

Storage — 0 Mtpa

Forsete carbon storage (EXL013)

Storage — 0 Mtpa

Havstjerne CO2 Storage (FSIU)

T&S — 0 Mtpa

NorDAC Kollsnes (Øygarden)

Full chain — 0.5 Mtpa

Norske Skog Skogn (Levanger)

CCU — 0.1 Mtpa

Treklyngen Bioforbrenning (Hønefoss)

CCU — 0.1 Mtpa

Fritos carbon storage (EXL014)

Storage — 0 Mtpa

Project Norway phase 2

Capture — 0.009 Mtpa

Project Norway phase 3

Capture — 0.03 Mtpa

Frevar KF / Kvitebjorn BIO-EL (Borg CO2) (2 facilities)

Capture — 0.12 Mtpa

HeidelbergMaterials Brevik

Capture — 0.4 Mtpa

Kollsnes DAC facility

Capture — 0.5 Mtpa

Lyse Forus Energigjenvinning Stavanger

Capture — 0.1 Mtpa

Altera Stella Maris CCS Project Phase 2

T&S — 3 Mtpa

Norske Skog Saugbrugs (Borg CO2)

Capture — 0.15 Mtpa

Northern Lights Phase 2

T&S — 3.7 Mtpa

Northern Lights Phase 1

T&S — 1.5 Mtpa

Hafslund Oslo Celsio

Capture — 0.35 Mtpa

Polaris offshore storage facility

Storage — 8 Mtpa

Sleipner

Full chain — 1 Mtpa

Snohvit CO2 capture and storage

Full chain — 0.7 Mtpa

Aukra Hydrogen Hub

Full chain — 0 Mtpa

Barents Blue ammonia project Train 1

Capture — 2 Mtpa

Barents Blue ammonia project Train 2

Capture — 2 Mtpa

HyDEMO (shelved??)

Capture — 0.15 Mtpa

Barents Blue ammonia project Train 3

Capture — 2 Mtpa

Errai storage project

Storage — 8 Mtpa

Luna storage

Storage — 5 Mtpa

Borregaard / SAE (Borg CO2) (2 facilities)

Capture — 0.15 Mtpa

BIR Waste-to-Energy Bergen

Capture — 0.1 Mtpa

EU2NSEA PCI Project

Transport — 20 Mtpa

Equinor Smeaheia storage phase 2

T&S — 24 Mtpa

Trudvang storage project (EXL007)

Storage — 10 Mtpa

STARFISH project (Havstjerne CO2 storage/Altera Stella Maris CCS Project Phase 1)

T&S — 4.275 Mtpa

Poseidon CO2 storage

Storage — 5 Mtpa

Equinor Smeaheia storage phase 1 (start up phase)

T&S — 5 Mtpa

Climeworks Norsk e fuel phase 1

CCU — 0.039 Mtpa

Gismarvik CO2 hub

Transport — 24 Mtpa

Climeworks Norsk e fuel phase 2

CCU — 0.035 Mtpa

Climeworks Norsk e fuel phase 3

CCU — 0.184 Mtpa