China published a coordinated batch of 12 national CCUS standards on 31 December 2025, with implementation from 1 July 2026. The batch establishes a common technical vocabulary and covers major interfaces across the CCUS chain, including post-combustion capture-system requirements and performance evaluation, CO2 stream quality and transport, geological storage, storage associated with CO2-enhanced oil recovery, and greenhouse-gas reduction accounting. Representative standards include GB/T 46877-2025 on general requirements for post-combustion capture systems, GB/T 46870.2-2025 on performance evaluation for capture plants integrated with power stations, and GB/T 46871-2025 on CO2 storage using enhanced oil recovery. Most instruments in the batch are GB/T recommended national standards: they improve technical consistency, procurement specifications, data comparability and project interfaces, but do not replace environmental approvals, injection licences, land or pore-space rights, or operator liability rules.
National Governance Context
China Overview
Aggregate National Maturity Index (Peak Strength)
Governed Policies
15
Identified Projects
49
Related Policy Network
Directly Linked Assets
Baotou Steel (Baogang Group) (Inner Mongolia) phase 1
Full chain — 0.5 Mtpa
Baotou Steel (Baogang Group) (Inner Mongolia) phase 2
Full chain — 1.5 Mtpa
CRP Haifeng Project (Guangdong)
Capture — 1 Mtpa
Yulin geological storage research facility and CCUS demonstration project (Shaanxi)
Storage — 0.1 Mtpa
Carbon Dioxide Full Oxygen Combustion Enrichment and Purification Demonstration Project Qingzhou (Shandong)
CCU — 0.2 Mtpa
CNPC 3 million tons Songliao basin demonstration (Heilongjiang)
Full chain — 3 Mtpa
Jinjiang Chemical CCUS Project (Xinjiang)
Full chain — 0.1 Mtpa
Xinjiang Dunhua Wucaiwan Industrial Park CO2 Capture Project (Xinjiang)
Full chain — 0.15 Mtpa
Xinjiang Guoneng Chemical Co CCU Phase 1 (Xinjiang)
Full chain — 0.1 Mtpa
Xinjiang Guoneng Chemical Co., Ltd CCU Phase 2 (Xinjiang)
Full chain — 0.2 Mtpa
Shaanxi Coal Group Yulin Chemical CCUS Phase 1 (Shaanxi)
Full chain — 0.4 Mtpa
Shaanxi Coal Group Yulin Chemical CCUS Phase 2 (Shaanxi)
Full chain — 0.6 Mtpa
Shaanxi Coal Group Yulin Chemical CCUS Phase 3 (Shaanxi)
Full chain — 3 Mtpa
Yanan Energy Chemical (Shaanxi)
Full chain — 0.8 Mtpa
Enping 15-1 offshore CCS (Hong Kong) (well extension)
Full chain — 0.1 Mtpa
Xinjiang Jinlong Shenwu Thermal Power Plant (Xinjiang)
Capture — 0.2 Mtpa
CPNC coal power Baijiantan Karamay (Xinjiang) Phase 2
Full chain — 1 Mtpa
Huaneng Shanghai Shidongkou Second Power Plant (Shanghai)
Full chain — 0.12 Mtpa
China Resources Tangshan Caofeidian Power (Hebei)
Full chain — 0.15 Mtpa
GreenGen Huaneng IGCC Project Phase III (Tianjin)
Full chain — 2 Mtpa
Sailboat Green Methanol plant Shengong petrochemical (Jiangsu)
CCU — 0.16 Mtpa
Karamay Dunhua methanol plant (Xinjiang)
Full chain — 0.1 Mtpa
Sinopec Nanjing Chemical Industries CCUS Cooperation Project (Jiangsu)
Full chain — 0.2 Mtpa
Sinopec Qilu Petrochemical Shengli (Shandong)
Full chain — 1 Mtpa
Sinopec Shengli Power Plant CCS (Shandong)
Full chain — 2 Mtpa
Yulin Coal Chemical CCUS (Shaanxi) Phase 1
Full chain — 0.3 Mtpa
Daya Bay CCS Hub phase 1 (Guangdong)
T&S — 2 Mtpa
Nanhai petrochemical plant-Capture for Daya bay CCS (Guangdong)
Capture — 0 Mtpa
Daya Bay CCS Hub phase 2 (Guangdong)
T&S — 8 Mtpa
Air Liquide Shanghai Chemical Industry Park (SCIP) decarbonisation (Shanghai)
Capture — 0 Mtpa
Beishui cement CCUS project (Beijing)
CCU — 0.1 Mtpa
Huaneng Longdong Energy base/Zhengning coal power plant (Gansu)
CCU — 1.5 Mtpa
Jidong cement carbon capture project (Hebei)
CCU — 0.1 Mtpa
Guanghui Energy CCUS integration project Phase 1 (Xinjiang)
Full chain — 0.1 Mtpa
Jiling Petrochemical CCUS (Nanjing refinery) (Jiangsu) phase 1
Full chain — 0.1 Mtpa
CEIC-CNPC CCUS-EOR demonstration (Ningxia) Phase 1
Full chain — 0.4 Mtpa
Changling Gas plant /Jilin Oil Field CO2-EOR Full-scale (Jilin)
Full chain — 0.6 Mtpa
China Energy Taizhou power (Jiangsu)
Full chain — 0.5 Mtpa
China Energy Guohua Jinjie Power (Shaanxi)
Full chain — 0.15 Mtpa
CEIC-CNPC CCUS-EOR demonstration (Ningxia) Phase 2
Full chain — 0.5 Mtpa
CEIC-CNPC CCUS-EOR demonstration (Ningxia) Phase 3
Full chain — 1.5 Mtpa
CEIC-CNPC CCUS-EOR demonstration (Ningxia) Phase 3 (dedicated storage)
Full chain — 0.5 Mtpa
Yulin Energy Chemical (Shaanxi)
Full chain — 1.6 Mtpa
Yulin Coal Chemical CCUS (Shaanxi) Phase 2
Full chain — 2.6 Mtpa
CPNC coal power Baijiantan Karamay (Xinjiang) Phase 1
Full chain — 1 Mtpa
Enping 15-1 offshore CCS (Hong Kong)
Full chain — 0.3 Mtpa
Junggar Basin Hub - Northwest phase 1 (Xinjiang)
T&S — 1 Mtpa
Junggar Basin Hub - Northwest phase 2 (Xinjiang)
T&S — 2 Mtpa
Junggar Basin Hub - Refinery Hydrogen (Xinjiang)
Capture — 1 Mtpa